July 26th, 2023       Notice #24 Hand Delivery & Owner Portal

 

Painting and Restoration
Buildings  1, 2, and 3 Units 581 –  653

 

There are some changes to the dates for pressure washing and painting as follows:

Building 3:

Pressure washing 3rd August.

Covering windows 4th August.

Priming and Painting 5th – 8th August.

Items that are not removed maybe removed by the contractors, and individuals will be charged for this.  Our contractors are not responsible for any damage or breakages.

Please remember to leave patio screen doors open.

Please ensure that pets and children are kept away from the work area at all times.

The buildings will be worked on in numerical order.

Once this work is nearing completion we will issue another notice with information regarding preserving the concrete and stucco work, so that it will not become damaged.

Thank you for your cooperation.

 

 

Sincerely,

At the Direction of the Board
BESPOKE CUSTOM PROPERTY MANAGEMENT AND CONSULTING SERVICES, LLC

Agent for The Village Townhouses-Jacaranda, Inc.